Current Schedule 

2017 asphalt overlay and full-depth reclamation project

Activity Location Earliest Start Date
Completed
Concrete removal and replacement
Johnson Drive, Johnson Court, Johnson Place, Dawson Drive, Dawson Court, Oak Ridge Drive, Valley Drive, Mikelson Boulevard, Black Feather Trail, and Meadows Parkway Bridge April 17
 
Asphalt patching
Dawson Court, Valley Drive, Mikelson Boulevard and Black Feather Trail. April 24
 
Overlay Dawson Court, Valley Drive, Mikelson Boulevard, Black Feather Trail, and Meadows Parkway Bridge May 15  
Full-depth reclamation Johnson Drive, Johnson Court, Johnson Place, Dawson Drive, and Oak Ridge Drive June 5  

2017 slurry seal project

Activity Location Earliest Start Date
Completed
Asphalt patching
Ridge Oaks Drive, Willow Oak Road, Live Oak Road, Live Oak Court, Valley Oak Court, Blue Oak Court, Valley Oak Road, Rock Lane, Rock Street, Columbine Drive, South St, S. Sierra Drive, Peak Vista Court, Brookside Circle, Stafford Circle, Easton Court, Malton Court, Brierly Court, Appleby Place, June Court, Wenlock Court, Faireham Court, Hawk Terrace, Eagle Tail Lane, Fox Haven Drive, Aspen Hollow Court, Bird Song Drive, Deer Valley Drive, Eagle Ridge Way, County View Way, Northview Place, Mountain Sky Drive, Flower Field Place, Heatherglenn Lane, Eagle Ridge Way, Idylwood Street, Copperfield Drive, Fawn Ridge Way, Echo Hollow Street, Journeys End Lane, Hillcroft Lane, Cool Meadow Place, Spring Ridge Trail, and Clearbrooke Court. June 19  
Slurry seal
Ridge Oaks Drive, Willow Oak Road, Live Oak Road, Live Oak Court, Valley Oak Court, Blue Oak Court, Valley Oak Road, Rock Lane, Rock Street, Columbine Drive, South St, S. Sierra Drive, Peak Vista Court, Brookside Circle, Stafford Circle, Easton Court, Malton Court, Brierly Court, Appleby Place, June Court, Wenlock Court, Faireham Court, Hawk Terrace, Eagle Tail Lane, Fox Haven Drive, Aspen Hollow Court, Bird Song Drive, Deer Valley Drive, Eagle Ridge Way, County View Way, Northview Place, Mountain Sky Drive, Flower Field Place, Heatherglenn Lane, Eagle Ridge Way, Idylwood Street, Copperfield Drive, Fawn Ridge Way, Echo Hollow Street, Journeys End Lane, Hillcroft Lane, Cool Meadow Place, Spring Ridge Trail, and Clearbrooke Court. July 5  

2017 curb, gutter, sidewalk and miscellaneous concrete projects

Activity Location Earliest Start Date
Completed
Remove and replace curb, gutter, and sidewalk
Ridge Oaks Drive, Willow Oak Road, Live Oak Road, Live Oak Court, Valley Oak Court, Blue Oak Court, Valley Oak Road, Rock Lane, Rock Street, Columbine Drive, South St, S. Sierra Drive, Peak Vista Court, Brookside Circle, Stafford Circle, Easton Court, Malton Court, Brierly Court, Appleby Place, June Court, Wenlock Court, Faireham Court, Hawk Terrace, Eagle Tail Lane, Fox Haven Drive, Aspen Hollow Court, Bird Song Drive, Deer Valley Drive, Eagle Ridge Way, County View Way, Northview Place, Mountain Sky Drive, Flower Field Place, Heatherglenn Lane, Eagle Ridge Way, Idylwood Street, Copperfield Drive, Fawn Ridge Way, Echo Hollow Street, Journeys End Lane, Hillcroft Lane, Cool Meadow Place, Spring Ridge Trail, and Clearbrooke Court. April 10
 

2017 reconstruction project

Activity Location Earliest Start Date Completed
Reconstruction Emerald Drive from Plum Creek Parkway to Emerald Court April 10  
Reconstruction Prestwick Way from Mount Royal Drive to Mount Royal Drive April 10  
Reconstruction October Place TBD  

2017 concrete pavement restoration project

Activity Location Earliest Start Date
Completed
Concrete pavement panel removal & replacement Wilcox Street and Mount Royal Drive April 10  
Concrete grinding  Mount Royal Drive TBD  
Joint sealing Prestwick Court amd Mount Royal Drive TBD  

2017 mastic and crack seal project

Activity Location Earliest Start Date
Completed
Mastic and crack sealing Crystal Valley, Memmen, Young/American, The Oaks, Plum Creek and Heckendorf Ranch. TBD TBD
ConeGuyThank YouSign
We'll be in touch!
While we work to improve roads in your neighborhood, we know it means a temporary inconvenience, so we want you to know what to expect in terms of timing and communication. 

If we will be working on your street, we will send you a letter about two weeks ahead of time, and our contractor will place a note on your door 48 to 72 hours before scheduled work. 

We appreciate your patience. Please know, sometimes, weather impacts our schedule. We will do our best to keep you notified.